Interior rearview mirror base bonding (2003)

Sealant height 0.12 in (3.0 mm); primer drying approximately 30 minutes. Surface hardening / return to service: approximately 1.5 h / 12 h at 41 °F (5 °C);1 h / 4 h at 68 °F (20 °C);10 min. / 2 h at 95 °F (35 °C).Sealant height 3.0 mm {0.12 in}; primer drying approximately 30 minutes. Surface hardening / return to service: approximately 1.5 h / 12 h at 5°C {41°F};1 h / 4 h at 20°C {68°F};10 min. / 2 h at 35°C {95°F}.

Factory manualTaken from a Mazda factory workshop manual, with page citation.
Procedure

For the original interior mirror base bonded to the windshield ceramic coating. Remove the mirror before base service. For piano-wire base removal wear gloves, wind each wire end around a bar, and use the entire wire length. Cut away all original sealant with a razor while wearing gloves. Clean and degrease the ceramic coating and base; keep them clean and do not touch prepared surfaces. Use glass primer on glass and body primer on the base; let primer dry approximately 30 minutes. Apply 3.0 mm {0.12 in} high sealant as the central patch and surrounding ring on the base, center the base in the ceramic coating, and press onto the glass. The source positioning figure shows a 5.0 mm {0.2 in} margin above the base. Remove excess sealant with isopropyl alcohol. Observe the factory surface-hardening and separate return-to-service times before completing mirror installation. This is the factory bonding process; it supplies no curing rule for an unspecified replacement adhesive.

Applies to
  • NB 2003 (BP-Z3)
  • Verified in: 2003 Mazda MX-5 Miata Workshop Manual (electronic manual capture)

Sources (1)

View 1 source citations
  • 2003 Mazda MX-5 Miata Workshop Manual (electronic manual capture)Tier 1
    Page Base Removal/Installation (PDF pp.1904–1906) · Printed value & notes
    Page Base Removal/Installation (PDF pp.1904–1906)
    Printed: “Apply a height of 3.0 mm {0.12 in} sealant to the base. Use only glass primer on the glass, and body primer on the base. Allow the primer to dry for approximately 30 minutes. Use isopropyl alcohol to remove any excess sealant. Temperature Surface hardening time Time required until vehicle can be put into service 5°C {41°F} Approx. 1.5 h Approx. 12 h 20°C {68°F} Approx. 1 h Approx. 4 h 35°C {95°F} Approx. 10 min. Approx. 2 h”